i <br />amec <br />Earth & Environmental <br />LOB EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 Project No.: 8420125EO <br />Owner: Cripple Creek & Victor Gold Mining Co. Contractor: Ames Construction Co. Inc. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ LOB <br />Date: 02/10/09 Reporting Period: 02/01/09 through 02/07/09 <br />Days S M T W T F S <br />Work Shifts D D D D D - <br /> <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Lows: 18° to 28° Highs: 38°to 59° <br />AMEC CQA Personnel On-site through the Reporting Period (See Attachment A). <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. LOB Pad <br />• No activities <br />2. LOB Delivery Road <br />• Ames continued to clear and grub. <br />Dandy slash stockpile. <br />The material was hauled to the Joe <br />B. Stripping <br />1. LOB Pad <br />• No Activities <br />2. LOB Delivery Road <br />• Ames continued to remove topsoil from the LOB Delivery Road from <br />station 2+50 to station 38+00 (see attached photos). The topsoil was hauled <br />and placed in the upper stockpile. <br />C. Waste Rock to Stockpile <br />1. LOB Pad <br />• No Activities <br />2. LOB Delivery Road <br />• No Activities <br />Sheet 1 of 10 LOB Weekly Report WE 02.07.09.D.doc