2500 Slurry Trench Excavation & Backlill
<br />2510 Slurry Trench Excavation & Backfili to 31' Deep 223,839 sf $ 2.19 $ 490,207.41
<br />2520 Key Excavation to 4' Deep 33,660 sf $ 5.98 $ 201,286.80
<br /> 2500 Slurry Trench Excavation & Backfill 257,499 sf $ 2.69 $ 691,494.21
<br />2700 Cap Construction
<br />2710 Cap Construction 8,415 If $ 5.49 $ 46,198.35
<br /> 2700 Cap Construction 257,499 sf $ 0.18 $ 46,198.35
<br />2800 Backffll Over Cap
<br />2820 Crossings Over Cap 3 ea $ 2,355.00 $ 7,065.00
<br /> 2800 Backfill Over Cap 1 Is $ 7,065.00
<br />2900 Leak Test
<br />2920 Leak Test for Reservoir# 2 1 Is $ 29,400.00 $ 29,400.00
<br /> 2900 Leak Test 1 Is $ 29,400.00
<br /> Total for Reservoir# 2 257,499 sf $ 3.36 $ 866,132.56
<br /> Reservoir# 3
<br />ITEM DESCRIPTION QTY UNITS UNIT PRICE EXTENSION
<br />500 Engineering & Quality Control
<br />510 Survey & Layout 1 Is $ 2,840.00 $ 2,840.00
<br />520 Engineering & Quality Control 1 Is $ 95,315.00 $ 95,315.00
<br /> 500 Engineering & Quality Control 1 Is $ 98,155.00 $ 98,155.00
<br />1000 General Conditions
<br />1030 Mobilization/Demobilization 11s $ - $ -
<br /> 1000 General Conditions 274,809 sf $ - $ -
<br />2500 Slurry Trench Excavation & Back ill
<br />2510 Slurry Trench Excavation & Backfill to 31' Deep 237,049 sf $ 2.29 $ 542,842.21
<br />2520 Key Excavation to 4' Deep 37,760 sf $ 5.96 $ 225,049.60
<br /> 2500 Slurry Trench Excavation & Backfili 274,809 sf $ 2.79 $ 767,891.81
<br />2700 Cap Construction
<br />2710 Cap Construction 9,440 If $ 5.49 $ 51,825.60
<br /> 2700 Cap Construction 274,809 sf $ 0.19 $ 51,825.60
<br />2800 Backtill Over Cap
<br />2820 Crossings Over Cap 6 ea $ 2,355.00 $ 14,130.00
<br /> 2800 Backfill Over Cap 1 Is $ 14,130.00
<br />2900 Leak Test
<br />2920 Leak Test for Reservoir# 3 1 Is $ 29,400.00 $ 29,400.00
<br /> 2900 Leak Test 1 Is $ 29,400.00
<br /> Total for Reservolr# 3 274,809 sf $ 3.50 $ 961,402.41
<br /> Reservoir# 4
<br />ITEM DESCRIPTION QTY UNITS UNIT PRICE EXTENSION
<br />500 Engineering & Quality Control
<br />510 Survey & Layout 1 Is $ 2,195.00 $ 2,195.00
<br />520 Engineering & Quality Control 1 Is $ 73,625.00 $ 73,625.00
<br /> 500 Engineering & Quality Control 1 Is $ 75,820.00 $ 75,820.00
<br />1000 General Conditions
<br />1030 Mobilization/Demobilization 11s $ - $ -
<br /> 1000 General Conditions 212,290 sf $ - $ -
<br />2500 Slurry Trench Excavation & Backfill
<br />2510 Slurry Trench Excavation & Backfill to 31' Deep 188,370 sf $ 2.17 $ 408,762.90
<br />2520 Key Excavation to 4' Deep 23,920 sf $ 6.38 $ 152,609.60
<br /> 2500 Slurry Trench Excavation & Backfill 212,290 sf $ 2.64 $ 561,372.50
<br />2700 Cap Construction
<br />Boral Aggregate Slurry Walls (don't use summary) - Reservoirs 1 - 5 Rev. 5 (9-18-08)
<br />9/18/2008, 12:02 PM Page 2
|