Laserfiche WebLink
were used to excavate the shaft. An additional concrete pad(s), nominal size of 40 by 100 feet by 2 feet <br />thick, was placed to accommodate the hoisting winch, transformers, distribution boxes, operator consoles, <br />surrounding building, and other miscellaneous equipment. <br />• Shaft excavation was completed as a progressive cyclic operation, with each excavation cycle consisting of <br />four basic operations; drilling, blasting, mucking, and concrete lining. Drilling involved the use of one or <br />more pneumatic shaft jumbo drills nested in a multiple-deck work stage. Blasting was completed using <br />permissible stick powder and electric detonators. The blasted shaft materials were mucked using in-shaft <br />pneumatic muckers and a nominal 3-4 yard hoisting bucket. The shaft cuttings were placed by a wheel- <br />loader in a 14-foot deep, lined temporary mine development waste pit excavated within the shaft pad, <br />adjacent to the shaft excavation, as shown on Maps EX16E-M1 and M2. The cuttings pit is lined with a <br />nominal 30-mil PVC flexible membrane liner having a permeability of ~10-'= cm/sec. The PVC liner is <br />covered with approximately 6-8 inches of pit-run material to protect the liner. The shaft concrete lining <br />was placed in nominal 20- to 30-foot lifts in cycle with the drilling and mucking operation, using acurb- <br />ring and slip-form assembly. During excavation, the shaft work area was ventilated using ventilation <br />ducting and a permissible surface fan. Once the blind sink excavation reached the coal seam, the work <br />stage was removed and disassembled. <br />The cuttings volume generated by shaft sinking operations is approximately 15,126 cubic yards (22,690 <br />cubic yazds when swelled by 50 percent, based on 20-foot diameter and 1,300-foot depth). If drainage of <br />water from the excavated material resulted in any significant accumulation of water in the cuttings pit, the <br />water was pumped to a water tanker to maintain essentially dry conditions in the pit. Upon completion of <br />the shaft excavation and concrete liner installation, any minor water accumulation in the cuttings pit were <br />allowed to dry-out, and the collection pit and cutting materials were then be covered with previously <br />placed materials from the shaft collaz excavation, graded, and revegetated with a temporary cover. A <br />sign(s) was posted designating the temporary mine development waste pit. The cuttings and shaft collaz <br />excavation materials will be utilized to re-fill the shaft during eventual reclamation of the facility, <br />• The cement liner serves to isolate the Twentymile Sandstone from the Wadge Overburden. As noted <br />above, apre-grout program is not required in a conventional blind sink. A probe-hole is typically carried <br />down the hole as the shaft is excavated. Water is grouted off from within the excavated shaft as it is <br />encountered. This further assures that, after final closure, the water in this unit is confined and will not <br />seep down on the inside of the shaft. Following completion of shaft excavation and cement lining <br />operations, and removal of equipment from the site, an emergency escape hoist will be installed in the <br />shaft. Hoist installation will involve completion of the following activities, as illustrated by the design <br />information provided in Exhibit 49N, 6MN Emergency Escape Hoist Design Drawings: <br />• Erection of apre-fabricated steel hoist-frame and bull-wheel, approximately 10 x 22 x 25 feet high <br />over the existing 6MN Ventilation Shaft, tying into the existing concrete shaft collar <br />• Fabrication of a steel frame and expanded metal shaft landing and access stairs, tying into the hoist- <br />frame <br />• Fabrication of a similaz shaft landing at the bottom of the shaft <br />• Installation in the shaft ofguide-ropes for the hoist cage <br />• Excavation for the hoist-house foundation <br />• Forming and pouring of the 20 x 30 foot reinforced concrete hoist-house foundation <br />• Installation of the hoist motor, winch, and associated control equipment on the hoist-house <br />foundation <br />• Erection of the pre-fabricated steel hoist house <br />• • Stringing of hoist cable and placement and connection of the 3 x 5 x 8 foot high pre-fabricated hoist <br />cage <br />• Electrical connections (from existing power distribution line) and testing of hoist <br />• Installation of appropriate equipment guazds and fencing <br />MR07-218 2.05 - 45.6d 07/26/07 <br />