Miscellaneous Utilities. Underground utilities, including phone lines, water <br />lines, and buried power lines that provide service to the Loadout, will be <br />abandoned in place. <br />Backfilling and Grading <br />Following building demolition and removal, the first major phase in the <br />reclamation of disturbed land is backfilling and grading the cut and fill areas. <br />This process is discussed in the Backfilling and Grading Plan found in Tab 18. <br />The first step is the determination of volumes. Cross sections were developed <br />in the rail spur area with the aid of a computer program from SoftDesk (see <br />Exhibit 18-2). Postmine slopes were then superimposed on the diagrams. For the <br />sake of continuity, it was estimated that all material would be graded toward <br />the railroad cut at slopes between 5H:1V and lOH:1V when sufficient adjacent <br />land was available. A digitizer was used to balance the cut and fill volumes of <br />material needed to create the above-described topography. This produced a final <br />topography that could not only be revegetated, but would also allow drainage to <br />flow through the reclaimed area without impounding water. <br />The CDMG utilized the CIRCES Cost Estimation Software to determine dozer <br />production. The program utilizes information given in the Caterpillar Handbook. <br />All tables and charts are computerized to simulate production for track type <br />equipment. See the various worksheets in Attachment 23-1 for production and <br />costs. <br />It is not anticipated that wheel type earthmovers will be needed to backfill the <br />cut areas. Sufficient material exists adjacent to the cut areas for backfill <br />purposes. <br />Facility Area. After the buildings and light poles are demolished and removed, <br />the facility area is reclaimed. Three feet of material will be ripped in the <br />facilities area. The top one foot of gravel/scoria surfacing on the <br />parking/storage areas will be dozed into cuts or low areas adjacent to the <br />facility. This material will be covered during the grading process. <br />Sediment Ponds. The two sediment ponds will be totally reclaimed. Locations of <br />the impoundments are shown on Exhibit 12-2. Material adjacent to the ponds will <br />be used to backfill the ponds. <br />MR-16 3 Revised 11/07 <br />