Third Party Oversight 1 Water, Waste & Land, Inc. <br />San Luis Mine January 10, 1993 <br />' 1.0 INTRODUCTION <br />' 1.1 BACKGROUND <br />This report documents the third-patty technical oversight at Battle Mountain Resources' <br />Inc. (BMRI) San Luis Mine in Costilla County, Colorado. This work was conducted for the Colorado <br />' Division of Minerals and Geology (DMG) and BMRI by Water, Waste & Land, Inc. (WWL) under the <br />October 15, 1993 Agreement for Third-Party Oversight and Review. The work was conducted <br />' as directed by DMG to provide technical review of issues related to design and construction of the <br />Phase II Raise I Expansion of the tailings disposal facility at the San Luis Mine. This expansion <br />' consisted of increasing the height of the tailings embankment by construction mf the Raise I <br />Embankment to elevation 8605 feet, and increasing the lined impoundment area within the tailings <br />facility to the ultimate tailings elevation. These two construction components are referred to as <br />the Raise I Expansion in this report. <br />During initial construction of the Raise I Expansion, issues were raised by the DMG <br />concerning construction materials and techniques being utilized and how those materials and <br />' techniques would affect the completed tailings impoundment system. The third-party technical <br />oversight was initiated to address these issues, and this report presents the results of this third- <br />party work. <br />1.2 PROJECT HISTORY <br />t A brief history of the San Luis Mine tailings disposal facility pertinent to the third-party <br />review is outlined below. <br />• November 1988 - BMRI submits a 112 Permit Application to the Mined Land <br />Reclamation Board (MLRB, later changed to the DMG) for the San Luis Project. The <br />Permit was revised in February 1989 and again in April 1989. <br />' • September 1989 -BMRI submits a 112 Permit Application Amendment to the MLRB <br />for the tailings disposal facility. <br />• March 1990 -MLRB approves the San Luis Project Permit Amendment for the tailings <br />' disposal facility. <br />• July 1990 to July 1991 -Construction of the Phase I Embankment and tailings <br />disposal facility. <br />' • July 12, 1993 -BMRI submits a letter of notification to the DMG concerning <br />construction of Phase II expansion of the tailings facility. <br />• July 22 -BMRI begins clearing and grubbing in preparation for the expansion of the <br />' liner system. <br />• August 23 -DMG gives approval for construction of the first 10 feet of the Phase II <br />Raise I Embankment. <br />• September 9 -Construction of the first 10 feet of the Raise I Embankment is <br />' completed. <br />• October 1 -The first DMG site inspection is conducted. <br />• October 4 -BMRI resumes construction of the Raise I Embankment. <br />1 <br />