<br />1 <br />1 <br />1 <br /> <br />1 <br />1 <br /> <br />1 <br />September 28, 1998 <br />If the surface of the fill becomes too dry or hard to permit suitable bonding with the <br />subsequent layer, the material shall be loosened by scarifying or disk harrowing, <br />moistened and re-compacted before an additional lift is placed. <br />B. Construction Rate <br />Construction of the embankment over the tailings surface may induce a state of <br />total stress within the tailings deposit resulting in a loss of strength. To prevent this <br />situation, the construction of the upstream embankment shall be paced to take not <br />less than one week. The controlled construction rate will allow excess pore <br />pressures developed during construction to dissipate. <br />Installation of standpipe piezometers will be under the direction of the engineer. <br />C. GCL/Geomembrane Anchor Trench Backfill <br />Material will be placed in the anchor trenches by the Contractor only after the <br />Engineer has granted approval that the geosynthetics have been properly placed <br />and tested in accordance with the specifications. <br />Backfill shall be carefully placed and spread in thin layers which shall not exceed <br />' 12-inches in thickness after mechanical compaction. Compaction shall be the <br />density of the surrounding material or as required by the Engineer. <br />' D. Construction Tolerances <br />The Contractor shall construct the embankment to the lines and grades shown on <br />' the Drawings, or as required by the Engineer, within the following tolerances: <br />The maximum permissible horizontal and vertical deviation of the <br />boundaries between the zones of the embankment from the lines and <br />' grades shown on the Drawings or as required by the Engineer shall be one <br />(1) foot. <br />• The finished upstream face of the embankment shall not deviate from the <br />line and grade shown on the Drawings, or as required by the Engineer, by <br />more than one (1) foot measured normal to the face and, in addition, shall <br />not be uniformly lower than the required line and grade. <br />• The line and grade of the finished downstream face of the embankment <br />' shall not deviate from that shown on the Drawing or required by the <br />Engineer by more than one(1) foot measured normal to the face and, in <br />addition, shall not be uniformly lower than the required line or grade. <br />' The elevation and width of the embankment crest shall not be less than the <br />dimensions shown on the Drawings or required by the Engineer. <br />' Earthwork <br />J:\5461\SPECSFNL.WPD 02200-9 <br />