<br />Henderson Mine, Permit #M-77-342 <br />Site Specific Reclamation Costs <br />Page 3 <br />B. SITE SPECIFIC RECLAMATION COSTS <br />The following are estimated costs of completing the reclamation of each specific site. Area <br />numbers aze correlated to the original reclamation map (not included with this report). Costs aze <br />1995 dollars and the numbers given below and throughout this section are thousands of dollars. <br />The individual items below were computed to the nearest one hundred dollars in a spread sheet <br />and then rounded to the nearest thousand dollars for this report. Therefore, some of the totals in <br />this section do not always add up. However, the total in part A of this document reflects the <br />spread sheet total to the nearest one hundred dollars. Acreages are projected through 1995. Areas <br />partially revegetated are itemized and assigned appropriate costs to complete the reclamation <br />from the present state of progress. As in the past, "buffer" represents land reserved far possible <br />future disturbance. <br />1. Mine site (172 acres) <br />a) Dismantle $ 0 <br />b) Grading and site preparation. $ 177 <br />c) Revegetate 116 acres (at $2,370/acre). $ 275 <br />d) Buffer, 56 acres ~4 <br /> Total... $ 452 <br />2. Vent shaft (1 acre) <br />a) Secure shaft opening. $ 52 <br />b) Fertilize (1 acre at $160/acre). $0 <br />Total... $ 52 <br />3. Portal area (28 acres) <br />a) Dismantle, close portal. $ 35 <br />b) Revegetate 3 acres (at $1,720/acre). $ 5 <br />c) Fertilize (25 acres at $160/acre, one application). ~~ <br />Total... $ 46 <br />4. Surface Railroad (121 acres) <br />a) Dismantle. $ 5 <br />b) Grading and site preparation. $ 68 <br />c) Revegetate RR bed (36 acres at $2,370/acre) $ 85 <br />d) Fertilize slopes (73 acres at $160/acre, 1 application) $ 12 <br />e) Buffer, 12 acres ~ 0 <br /> Total... $ 170 <br />