Pennittee: WHITEWATER BUILDING MATERIALS CORP, PAGE 2 <br />Permit #: M-77.129 <br />Operation Name: WHITEWATER 500 PIT <br />Anniversary Date: 09/22/06 <br />(2) Sloping was complete on 1,855 feet around perimeter of <br />Phase 2 - PART A (green) and 740 feet of slope in the north- <br />east part of Stage 2 - PART B. The blue cross hatched areas <br />show where we have material stored to create slopes in <br />Stages 2 - PARTS A & B. Only the final grading is necessary <br />on these areas. Overburden stockpiles have been placed <br />along the tops of these slopes for resoiling when they are <br />complete. <br />Reclamation is complete in the 20.0 acre area in Stage 4 - <br />PART B where borrow material was removed. The area was <br />seeded during the spring of 2005. We continue to monitor <br />the area and if needed, additional seeding will be done. <br />This area will eventually be mined. <br />There is approximately 20,000 cy of overburden stored in <br />Phase 2 - PARTS A, & B & Phase D that will be used on the <br />alpha stages and in Phase 2 - PART A as needed (orange). <br />These piles are in a constant state of flux with material <br />being added and removed as areas are stripped and resoiled. <br />The settling pond is still being used to clean process water <br />(gray). The stockpiles on the lake bottom in Phase 2 - PART <br />A will be removed or leveled as needed. The access corridor <br />is being utilized to cross the highway when material from <br />the mined area is moved to the plant (heavy blue line). <br />Phases X, Y, & 1 were prepared and seeded per the approved <br />plan in the fall of 2004. We continue to monitor the work <br />done to date and some remedial work may be needed in the <br />future. Please refer to the 1999 annual report map for <br />location of these areas. <br />Weed control continued this year on the area around the <br />active mine and on the area around Phase 1. We sprayed <br />Knapweed and White Top on October 6 & 7, 2005 and on May 24 <br />and June 14, 16, 19 & 20, 2006 with water soluble 2-4-D and <br />Curtail'". Spraying is finally beginning to have positive <br />results against the Knapweed and White Top. This is still <br />an uphill battle since there is little or no control taking <br />place on properties surrounding the mine and seed is being <br />wind blown in from offsite areas that we have no control <br />over. Spraying will continue as needed. The U.S. Fish and <br />Wildlife Service will not let us spray within 10 feet of the <br />lake in Phase 1. <br />(3) Mining will continue on Stage 2 - PART B this year working <br />to the south and on the floor of Stage 2 - PART A until all <br />material is removed from the Stage. In Stage F the mine <br />face will continue to move to the east. If more area is <br />needed, we will resume stripping ahead of the mining face. <br />