• 4.3 New Findings or Developments <br />4.3.1 1991 Operation Results <br />a. 1991 mining activities started in February and extended into August. <br />A summary of results follows: <br /> Recovery Tons Cum. <br /> Gallons Temp. % Bicarb Halite Mined" Tons <br />' Feb 4,701 155 9.7 3.9 50 50 <br />Mar 13,080 171 8.7 8.9 250 300 <br />Apr 18,073 189 8.4 6.9 465 765 <br />May 10,841 181 6.8 11.1 176 941 <br />Jun 11,364 201 8.4 6.5 943 1,884 <br />Jul 7,413 194 10.9 2.0 802 2,685 <br />Aug 7,741 194 11.5 1.1 1,114 3,800 <br />• Note: This total tons produced is an adjusted figure from Monthly <br />Reports based on more accurate truck scale weight data. Production <br />shown is greater than figure reported in Section 3.1.4 as material <br />mined includes = 328 tons in process pond. <br />b. As illustrated in operation results (Section 4.3.1a1, bicarb saturation <br />of the pregnant liquor was not achieved during 1991, resulting in <br />moderate values for percent bicarb and specific gravity. Nahcolite did <br />not leach as readily as expected. However, with time (February - <br />August) saturation values increased, and with processing experience, <br />the differential between pregnant and barren liquor values for specific <br />gravity increased (see Figure 4-31. This increase resulted in increased <br />bicarb production (see Figure 4-4). <br />i <br />19 <br />