Laserfiche WebLink
APPENDIX 2.05.4-5 (Continued) <br />• Cost Breakdown (continued): <br />(9) Pipe installation: 2 @ E100.00 ea 200.00 <br />(10) Riprap: 18 cy @ E25.00/cy 450.00 <br />(11) Unlined ditch construction: <br />200 cy @ E5.00/cy 1,000.00 <br />Total Sediment Pond Costs 18,672.00 <br />TOTAL EARTHWORK COSTS 5596,446.00 <br />C. Revegetation <br />1. Fertilization - 70 acres were fertilized <br />a. Equipment - Tractor and sprayer <br />b. Cost - E.75/lb @ 100 lbs/ac x 70 ac E 5,250.00 <br />2. Seeding - 1,420 lbs @ b16.00/lb 22,720.00 <br />• 3. Mulching - assume 1 ton mulch/acre <br />E425.00/ton x 70 ac 29,750.00 <br />(included in Revegetation Estimate) <br />Total Revegetation Costs 57,720.00 <br />D. Fencing - instilled 9,500 ft. around <br />perimeter @ E.95/ft 9,025.00 <br />E. Diversion ditch construction - 2,600 In ft <br />@ E3.00/ft 7,800.00 <br />F. Restoration and cleanup 2,500.00 <br />• <br />- 362 - (Rev. 5/86) <br />