Laserfiche WebLink
<br />The final grading of the waste dump, application and compaction of <br />• the clay cover, and construction of the diversion channel will require <br />approximately two to three months. <br />The early spring application of topsoil and mulch and tie prepara- <br />tion of the seedbed will require approximately one month. S~~eding <br />operation will follow, probably requiring approximately one iueek. <br />The application of fertilizer subsequent to seeding during the <br />first through the third growing season will be projects of short <br />duration, requiring about one week. <br />All necessary vegetation management will continue until a long- <br />lasting vegetative cover has been established and the reclam<<tion per- <br />formance objectives have been met. <br /> <br />E-17 <br />