Laserfiche WebLink
II. Material Disassembly and Loading <br />• a) Transformer <br />Approximate size 11.5' X 8' X 11' <br />Remove from pad and place on trailer <br />Assume cost of $202.00/hr for labor and equipment <br />2 hours X $202/hr = $404.00 <br />b) H-frames <br />Approximate size 15' (2 posts) 10' (cross post) for each <br />H-frame for a total of 9 posts <br />disassemble and load on dump trucks or trailer (2 laborers) <br />$37.80 X 2 hours = $75.60 <br />c) Concrete pad removal <br />Approximate size 12' X 6' X 1' = 2.7 CY <br />Removal/load cost - $3.70 CY <br />2.7 CY X $3.70 = $9.99 or $10.00 <br />• III. Total cost for substation dismantling and removal - $512.10 or <br />$512.00 <br />B. Stoker Oiling System <br />I. Tank removal <br />Remove from area and place on flat bed truck <br />Assume cost of $202/hr for labor and equipment <br />.5 hr X $202/hr = $101.00 <br />II. Concrete removal <br />Approximate size <br />Slab 6' X 9' X <br />Walls: 2 each 6' <br />2 each 9' <br />Assume removal <br />4.78 CY X $3.7 <br />1' = 54 ft' <br />X 2.5' X 1' <br />X 2.5' X 1' <br />and load cos <br />CY = $17.69 <br />2.00 CY <br />30 ft' = 1.11 CY <br />45 ft' = 1.67 CY <br />t of $3.70 CY <br />or $18.00 <br />. III. Total Cost for Stoker Oiling System Loading and Removal = $119.00 <br />780-141 (f) <br />