D. Total Cost <br />• I Substation = 512.00 <br />II Stoker Oiling System = 119.00 <br />III Transport = 325.00 <br />956.00 <br />IV 10% Administrative Fee 95.60 <br />Total $1051.60 <br />or $1050.00 <br />Coal Storage Pad & Culvert Removal <br />Coal Storage Pad <br />A. Regrade Pad and ramp <br />8 hours X $170.30/hr = 1362.00 <br />• B. Reapply Topsoil <br />3II700 CY <br />600 CY/hr = 64.5 hrs <br />64.5 hrs X $1LO/hr = 7740.00 <br />C. Seed <br />12 acres X $200/ac = 2400.00 <br />Culvert Removal <br />General Labor <br />8 hours X $15/hr = 120.00 <br />$11,622.00 <br />10 % Administrative 1162.00 <br />$12,784.00 <br />Say $12,800.00 <br />• <br />MR 90-48 780-141(h) Revised 04/12/90 <br />