Phase IV Weekly Summary No. 28 Page 2 <br />003-2203 <br />Caterpillar 966 loader and placed in the random fill construction area, northeast of the compacted SF <br />footprint, where the Arequa gulch sedimentation pond will later be constructed. <br />. Ames conducted slope re-contouring in the Phase Na azea included blasting east of the existing <br />HWY 67, at Permanent Diversion Channel stations 34+00 through 40+00 on August 13`h through <br />16a'. <br />No confirmation drilling or underground working remediation occurred within the Phase IVa azea <br />during this reporting period. <br />Phase Nb <br />Ames continued placement and compaction efforts of SF, west of the active crusher, for the new <br />LOB construction subgrade. Ames placed SF in approximately 2-foot lifts, removed oversized and <br />deleterious material (roots, branches), moisture conditioned, and compacted the fill which was <br />borrowed from the Phase IVa slope excavation and the Phase Nb and IVc local borrow located <br />north of the active fill. Compaction was attained by use of a smooth drum vibratory compactor and <br />supplemented by haul trucks splitting their tracks across the fill. <br />No confirmation drilling or underground working remediation occurred within the Phase IVb azea <br />during this reporting period. <br />Phase Nc <br />~ • Ames continued some rough slope re-contouring within the Phase IVc azea by removing cut material <br />and placing it in the Phase IVb LOB ftll. <br />Ames conducted confirmation drilling at UG-236, and began confirmation drilling at UG-294B. <br />Ames was unable to confirm any new underground working at either UG-236 or UG-294B. Botl• <br />workings drilled during this reporting period remain outstanding as drilling is incomplete to date. <br />(See Attachment A for approximate construction locations for all Phase N areas.) <br />Field Monitoring and Testing Activities <br />Golder observed clearing and grubbing activities in Upper Arequa Gulch (Phase IVa). Clearing and <br />grubbing activities were conducted within the clearing limits. <br />Golder monitored SF placement in alI the Phase IV areas including, verification of lift thickness, <br />material, compactive effort, particle size, and temperature for compliance with the drawings and <br />specifications. Three nucleaz moisture density tests were performed on the Phase Nb LOB area and <br />passed SF compaction specifications. No moisture/density tests were performed on SF in the Phase <br />IVa azea during this reporting period, as material was an-testable per ASTM D698, based on <br />laboratory testing and visual determination. Golder observed the removal of oversized and <br />deleterious material from the fill. <br /> <br />PAue Na 2B Augi2-tB.doc Golder Associates Inc. <br />