My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
PERMFILE129033
DRMS
>
Back File Migration
>
Permit File
>
300000
>
PERMFILE129033
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 10:26:07 PM
Creation date
11/25/2007 7:01:43 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
Permit File
Doc Date
9/3/2002
Doc Name
Certification Report Weekly Summary No. 26
From
Cripple Creek & Victor Gold
To
DMG
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
41
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Phase IV Weekly Summary No. 37 Page 2 <br />loaded several 777 haul trucks. The material was then hauled to the Arequa Gulch fill azea. SF <br />materials were placed in horizontal lifts typically not exceeding 2 foot in loose thickness. A <br />Caterpillaz CS563C roller provided compactive effort, while a Caterpillar water wagon provided <br />moisture conditioning when needed or required. SF material would also be placed in the <br />uncontrolled azea to the north of the fill when needed. <br />Ames loaded out selected rip-rap material from blasted rock shot azeas neaz UG-445 and UG-446 <br />(DIO hilt) by use of a Cat 375 track-hoe or a Cat 992 loader and several Cat 777 haul trucks. The <br />material was then hauled to the Ames crusher azea for further processing. <br />Ames began excavation and removal of the old existing highway 67 asphalt and guardrail. A Cat <br />3751oaded several Cat 777 haul trucks, which then hauled the waste to the sky dump. <br />Ames blasted underground laterals at UG-456 on Wednesday. <br />Ames performed blast-drilling activities on Monday through Friday during this reporting period, in <br />the central and southern portion of the Phase IVa azea. Blasting occurred Wednesday, Thursday, and <br />Friday during this reporting period. <br />Phase IVb <br />Ames performed excavation remediation activities for known underground workings UG-238, 241, <br />251, and 252. If the workings were verified as shallow, a Cat D7 dozer and a Cat 563 roller would <br />backfill the excavations and compact the shaft back to grade with SF. Otherwise, the shaft was left <br />• open for further remediation to be performed later. <br />Ames performed grubbing and clearing of topsoil and removed trees. A Cat D7 and a Cat 330 track- <br />hoe removed trees and stripped topsoil from the southwestern area of Phase IVb. Topsoil and slash <br />were piled locally for relocation at a later date. <br />Ames did not perform any drilling activities associated with the Phase IVb construction azea. <br />Phase IVc <br />Ames performed excavation remediation activities for known underground workings UG-236, 239, <br />239B, 239C, 239D, 239E, 239F, 240, 246, 254, 255, and 256. If the workings were verified as <br />shallow, a Cat D7 dozer and a Cat 563 roller would backfill the excavations and compact the shaft <br />back to grade with SF. Otherwise, the shaft was left open for further remediation to be performed <br />later. <br />Ames performed grubbing and cleazing of topsoil and removed trees. A Cat D7 and a Cat 330 track- <br />hoe removed trees and stripped topsoil from the southwestern azea of Phase IVc, near the existing <br />topsoil pile, west of the Phase IVc limits. Topsoil and slash were piled locally for relocation at a <br />later date. <br />Ames performed confirmatory drilling activities associated with the Phase IVc construction area, on <br />LJ <br />PhuelVsl]Oa19-Op20.doc Golder Associates lnc. <br />
The URL can be used to link to this page
Your browser does not support the video tag.