Laserfiche WebLink
IV. IMPLEMENTATION <br />A. Schedule <br />The site-specific implementation schedule for this plan coincides with the <br />operational schedule of the Camenish Borrow site. Borrow pit preparation work is <br />anticipated to begin December 2006 to be fotlowed by the excavation of borrow material <br />(sand and gravel) beginning January 2007 and pit reclamation beginning in the fall of <br />2007 and ending in the spring of 2008. <br />NOTES: A. IMPLEMENTATION SCHEDULE <br />Develop a schedule for implementation. For example, the schedule for this site might <br />include a deadline for putting housekeeping measures into practice. Some controls may <br />be immediately put into action; others will be phased in. Assign specific individuals with <br />responsibility for implementing aspects of the plan. <br />33 <br />