• Topsoil replacement requirements were determined by multiplying <br />disturbance area acreages by required replacement thicknesses. All other <br />material volumes were taken from the existing bond estimate. <br />CALCULATION OF EQUIPMENT PRODUCTIVITIES <br />Equipment productivities where given were taken from the existing bond <br />estimate. If the equipment productivities were not given, EFCI calculated <br />them using methods and guidelines from the "Caterpillar Performance <br />Handbook, Edition 18". All productivities were adjusted to reflect <br />equipment utilization. <br />DETERMINATION OF EQUIPMENT HOURS <br />Calculation of equipment hours required to complete each reclamation <br />function involved dividing material handling volumes by adjusted <br />productivity rates. <br />DEVELOPMENT OF EQUIPMENT. LABOR, DEMOLITION AND REVEGETATION UNIT COSTS <br />All unit costs utilized in preparation of the bonding cost estimate have <br />been obtained from published reference sources, previous bond estimates, <br />or past mining experience. The objective in developing specific cost <br />information has been to identify costs which are representative of those <br />which would actually be incurred for the contemplated reclamation work at <br />this site. <br />All equipment rental costs were obtained from Wagner Equipment Co. Rental <br />Rates. Equipment operating costs were obtained from the CRG. Both rental <br />and operating costs are based on a one (1) shift per day operating <br />schedule. <br />Most of the unit costs for facilities demolition were obtained from the <br />MCD. All other unit costs either came from the existing bond estimate or <br />were based on EFCI's past mining and reclamation experience. <br />Unit costs for riprap and revegetation came from the existing bond <br />4 <br />