• ' C ~~i <br />RECLAMATION PLAN AND TIMETABLE EXHI <br />1. General Reclamation Plan <br />Once this mining is completed, the subsoil and topsoil from the stockpiles will be replaced on the <br />mined area of Phase 2. Additional subsoil from the sediment sump dam will be used to regrade the <br />area around [he power poles to a mild slope (2.OH:1.OV). Assuming that mining starts in the sum- <br />mer of year 2000, the reclamation will commence in the spring of the year 2007. No backfilling of <br />the sideslopes will be needed to attain a 2.OH:1.OV slope, since the material will be excavated to this <br />slope during mining. The final post-mining land use is identical to its existing use of dryland graz- <br />ing. The worst case cost for reclamation of the site will occur when the Phase 2 has been mined out <br />but no topsoil or subsoil has been restored to [he area from the stockpiles. The Phase 1 area will <br />have been reclaimed and revegetated by this time. The stages of the reclamation plan and the worst <br />case reclamation costs are given below: <br />Task # Description Time (hrs) Cost <br />1 Spread subsoil on Phase 2 area from stockpile 51 $5,829 <br /> (130,680 cubic feet or 4,840 cy) Avg, haul dist = <br /> 440 feet @ +1% grade. Use D-8 w/universal <br /> blade. Cost is $1.067/cy. See attached sheet. <br />2 Final grading of pond (300 cy) Use Cat D8 - 4 $456 <br /> $114/hr x 4 hrs) <br />3 Spread topsoil on Phase 2 area from stockpile 21 $2,400 <br /> (54,432 cubic feet or 2,016 cy) Avg. haul dist = <br /> 440 feet @ +1% grade. Use D-8 w/universal <br /> blade Cost is $1.067/cy. See attached sheet. <br />4 Final grading and harrowing of topsoil(2016 cy @ 8 $766 <br /> $0.38/cy). All berms and ditches are removed for <br /> this phase. <br />5 Seed, mulch, fertilize (3.1 acres@ $700/acre) 12 $2,170 <br /> Total Direct Costs 96 hrs $11,621 <br /> DMG Costs (14.5% x direct costs) $2,266 <br /> Total Bond Amount $13,887 <br />Ferrero Pit 2/00 21 <br />