• III. Area 41 <br />A. Site Preparation <br /> 1. Topsoil Removal <br /> a. 21 acres require topsoil salvage (50,820 yd3) <br /> b. Same assumption as in Production estimates <br /> 21 acres x 43,560ft2/ac x 1.5' dew = 50,8 20 yd3 <br /> 27ft3 <br /> 2. Spoil Grading - 21 acres <br /> 3. Channel Construction - Excavate 70,000 yd3 <br />B. Riprap and bedding haul and placement <br /> 1. Riprap - 2,100yd3 <br /> 2. Bedding - 820 yd3 <br />C. Reclamation <br /> 1. Spoil grading - 21 acres <br /> 2. Topsoil redistribution - 50,820yd3 <br /> 3. Revegetation - 21 acres <br />• <br />• <br />- 44 - Revised 05/26/87 <br />