DRILLING SCHEDULE <br />MCC will proceed with road construction and drilling activities upon final <br />approval of Federal and state permits anticipated on July 26, 2002. A schedule of drilling <br />is presented based on that date. Drilling is presumed to require 7 days per hole including <br />mobilization from site to site, setup, drilling, and rig down. <br />MDW ID Number Start Finish <br />16-01 Aug 1 Aug 8 <br />16-02 Aug 2 Aug 9 <br />16-03 Aug 9 Aug 16 <br />16-04 Aug 16 Aug 23 <br />16-OS Aug 23 Aug 30 <br />16-06 Aug 30 Sept 6 <br />16-07 Sept 6 Sept 13 <br />16-08 Aug 8 .Aug 16 <br />17-01 Aug 16 Aug 24 <br />17-02 Aug 24 Sept 1 <br />17-03 Sept 1 Sept 9 <br />17-04 Sept 9 Sept 17 <br />17-OS Sept 17 Sept 25 <br />17-06 Sept 13 Sept 21 <br />17-07 Sept 25 Oct 3 <br />17-08 Sept 21 Sept 29 <br />17-09 Oct 3 Oct 11 <br />Delays due to mechanical breakdowns, inclement weather, hole conditions, <br />operational requirements, and permit approval aze not represented in the schedule. MCC <br />will be contracting for two drill rigs to complete this aggressive schedule. <br />12 <br />