Table 4.4.3-1 <br />Time <br />Fall, 1980 <br />• <br />l J <br />Interim Reclamation Timetable. <br />Spring, 1981 <br />Description <br />1. Completion of construction earthwork. <br />2. Erosion control measures: <br />a) erosion bales; <br />b) temporary berms, ditches, or other <br />diversion structures; <br />c) construction of sediment traps as <br />required. <br />3. Interim soil stabilization: <br />a) hydromulch and seed soil and fill <br />stockpiles; <br />b) hydromulch, seed and fertilize non- <br />operational dryland disturbed areas <br />(seed mix #5); <br />c) hydromulch, seed and fertilize non- <br />operational irrigated disturbed <br />areas (pasture mix). <br />1. Final landscape earthwork: regrade <br />stockpiles, berms, pond perimeters, etc. <br />2. Fine grading and filling of all nonopera- <br />tional disturbed areas. <br />3. Plant nursery stock. <br />4. Seed irrigated areas, mulch and fertilize. <br />4-75 <br />