Laserfiche WebLink
4 Use part of overburden stockpile to backfill majority of 1:1 0.4 <br /> slopes in Phase 1 area to 3H:1V. <br />4 Remove mining equipment, al]ow lake to fill. 0.1 <br />5 Site sits idle for 7 months 7.0 <br />6 Move topsoil and overburden from Phase 2 into bottom of 0.3 <br /> excavation of Phase 1. <br />7 Mine Phase 2 (140,000 tons) 3.5 <br />8 Use overburden from stockpiles and Phase 1 area to back- 0.5 <br /> fill slopes to 3:1. <br />9 Replace topsoil on disturbed area from stockpile. Only 2.5 0.5 <br /> acres of the 9.75 acre permit area will be stockpiled since <br /> most of the area will be underwater. The amount moved <br /> will be 5400 cy. <br />10 Reseed lake edges with wetland mix and upper areas with 0.2 <br /> rangeland mix. <br /> TOTAL MONTHS 15.8 <br />19 Road Pit 10/02 16 <br />