Laserfiche WebLink
Task Description Time Needed Cost <br /># months <br />1 Regrade 1.95 acres of sediment ponds, ditches, 1.0 $1330 <br /> traps, etc. Use D8 dozer@ $0.38 per cy for <br /> 3500 cy <br />2 Move topsoil from stockpile with loader and 0.4 $4013 <br /> truck. Spread the soil on the area from Task 1 <br /> and the remainder on the flat area. Use D-8 <br /> dozer for spreading = 3237 cy @ $1.24 per cy <br />3 Move overburden from stockpile on 7.0 acres 0.4 $5062 <br /> of flat area. Use 627 Scraper. 14888 cy @ <br /> $0.34 per cy <br />4 Regrade overburden with D-8. Short dozer 0.4 $2977 <br /> push. 14888 cy @ $0.20 per cy. <br />5 Disc overburden on 7.0 acres of flat area. Use 0.2 $1,400 <br /> D8 Dozer. $200 per acre x 7.0 acres <br />6 Install imgation ditch 1' deep 1260' long 2:1 0.2 $1240 <br /> slopes = 93 cy Use D-8. 10 hrs x $124/hr <br />7 Reseed, mulch and fertilize all topsoiled areas. 0.1 $10125 <br /> Drill seeding and crimp mulching will be <br /> employed on flat azeas and broadcast seeding <br /> will be done on the slopes greater than 3H:1 V. <br /> Cost is $750/acre x 13.5 acres <br />8 Assume 1 acre of slope will be planted with 0.0 1200 <br /> special seed mix, dead trees and pinon juniper <br /> tubules $1200/acre x 1.0 acres <br /> Totals 2.7 $27,627 <br /> DMG Costs (21% x direct costs) $5,802 <br /> Total Bond Amount $33,429 <br />Bellgazdt Pit 1/06 44 <br />