I • RECLAMATION TIMETABLE <br />LJ <br />Task Description Time Needed <br /># months <br />1 Construct Sediment Trap to the southwest of Strip 2. Install Collection 0.5 <br /> Ditch #1 leading to it. <br />2 Mine Strip 2. (2.60 acres) after moving excavated topsoil to stockpile. 24 <br /> Use overburden to backfill 1.7 acres of older exposed flat azea that <br /> was mined out previously. <br />3 Strip soil and overburden from Strip 3 (4.47 acres). Place topsoil in 1 <br /> stockpile. <br />4 Mine Strip 3. (4.47 acres) Move excavated topsoil to stockpile. Use 61 <br /> overburden to backfill 1.0 acres of older flat area and place the <br /> remaining overburden in the stockpile. <br />5 Move facilities closer to mining area immediately east of Strips 3. 1 <br />6 Strip soil from Strip 4 and place on south facing slopes of Strip 3. 1 <br /> Move overburden from Strip 4 (3.50 acres) and place in 3.5 acres of <br /> final graded area of Strip 3. <br />7 Mine Strip 4 (3.50 acres). Remove portable facilities. 37 <br />8 Using overburden from stockpile, backfill remaining portions of flat 1 <br /> areas of facilities area and Strip 4. <br />9 Regrade sediment ponds, ditches, stockpile azeas and sediment trap. 0.5 <br /> Total months 127 <br />4. Post-Reclamation Site Drainase <br />The entire permit area will drain to the south after reclamation, as shown on Map F. This is the <br />original drainage direction towazd Ellison Gulch and Cedaz Creek along Highway 50. As previously <br />Bellgazdt Pit 1/06 <br />26 <br />