• RECLAMATION PLAN - RULE 2.05.4 <br />All reclamation at the Bear No. 3 operation will be conducted following <br />the closure of the mining operations. The following represents a basic <br />time table for completion of the major steps of reclamation: <br />• Sealing of portals - 1 month <br />• Backfilling the portals and Aorta] area - 1 month <br />• Removal of surface structures - 2 months <br />• Smooth grade the area - 1 week <br />• Redistribution of topsoil - 1 week <br />• • Revegetation of the area - 3 days (revegetation will be done in <br />late September or early October) <br /> <br />-41- <br />