• When approved by the DMG, ponds 6 and 10 will be reclaimed. Material <br />will be placed into the ponds to convert the embankments from Coal <br />Creek Channel berms to solid banks. Material to backfill pond 10 will be <br />obtained from the pond embankment, the surrounding area and CBA-2. <br />Material necessary to backfill pond 6 will be primarily from CBA-2. The <br />run-off collection ditches from the refuse piles will be routed through the <br />backfilled ponds as shown on Exhibit 9C. Approximately 9,000 cubic <br />yards will be borrowed from CBA-2 to backfill pond 6 and 4,000 cubic <br />yards to backfill pond 10. <br />C J <br />• <br />14-11 i (Rev. 6/01) <br />