-4- <br />14. THREE h10NTHS PRIOR TO CONSTRUCTION OF THE ACCESS ROAD TO POND F, <br />PLANS FOR THIS ACCESS ROAD CERTIFIED BY A REGISTERED PROFESSIONAL <br />ENGINEER MUST BE SUBMITTED TO THE DIVISION IN ACCORDANCE FIITH THE <br />REQUIREMENTS OF RULE 4.03.2. DIVISION APPROVAL FOR CONSTRUCTION OF <br />THIS ACCESS ROAD A1UST BE OBTAINED PRIOR TO ANY CONSTRUCTION OF THIS <br />STRUCTURE. <br />15. THE APPLICANT MUST CONFIRM THAT RECLAMATION DELINEATED IN PHASE I <br />HAS BEEN ACCOMPLISHED. THIS A1UST INCLUDE ONE TRANSECT ACROSS THE <br />POST-MINING SURFACE DEMONSTRATING THAT THE PROPOSED SURFACE TOPOG- <br />RAPHY HAS BEEN ACCOMPLISHED. THIS CONFIRMATION MUST BE SUBMITTED <br />TO THE DIVISION PRIOR TO SUBMITTING THE BOND. <br />16. A PERFORMANCE BOND IN THE AMOUNT OF $550,249.00, PAYABLE TO THE <br />STATE OF COLORADO, MUST BE FILED WITH THE DIVISION IdITHIN 30 DAYS <br />FOLLO1dING FINAL APPROVAL OF THIS PROPOSED DECISION TO APPROVE THE <br />P ERAIIT . <br />17. EACH SCHEDULED INCREMENTAL BOND AMOUNT MUST BE FILED SdITH THE <br />DIVISION AT LEAST THIRTY 930) DAYS PRIOR TO THE COMMENCEMENT OF <br />SURFACE COAL MINING AND RECLAMATION OPERATIONS IN THE INCREMENTAL <br />AREA CORRESPONDING TO THAT BOND AMOUNT. CONFIRMATION THAT <br />RECLAMATION SCHEDULE IN THE PREVIOUS PHASE OR INCREMENT MUST <br />ACCOMPANY THE BOND APIOUNT SUBMITTED TO THE DIVISION. <br />18. THE APPLICANT MUST IDENTIFY ON MAP 17, PRE-MINING TOPOGRAPHY, ALL <br />OF THE AREAS THAT FALL UNDER THE CATEGORY OF STEEP SLOPE MINING. <br />THE STEEP SLOPE CATEGORY DOES NOT APPLY TO AREAS THAT HAVE BEEN OVER- <br />STEEPENED BY PREVIOUS MINING. THE APPLICANT DT11ST THEPI DEMONSTRATE <br />COMPLIANCE WITH RULE G,27 FOR THE IDENTIFIED STEEP SLOPE AREAS. THE <br />MAP AND DEMONSTRATION MUST BE SUBMITTED TO THE DIVISION WITHIN 120 <br />DAYS OF PERMIT ISSUANCE. <br />