1.2 Execution <br />Mobilization <br />Upon receipt of the Notice to Proceed, the CONTRACTOR shall furnish, mobilize, <br />move in, and install such temporary works, equipment and construction plant as <br />are necessary for the successful completion of the work. The CONTRACTOR shall <br />also operate and maintain such temporary works, equipment and construction <br />plant throughout the period of construction. All applicable temporary works, <br />such as sanitation facilities shall fully comely with any rules and <br />regulations. <br />Clearing and grubbing operations necessary for the temporary works, if any, <br />shall also be included as mobilization. <br />Oemobilization <br />Upon completion of the work under this Contract, the CONTRACTOR shall remove <br />all temporary works, equipment and construction plant. The CONTRACTOR shall <br />remove from the work site all rubbish, unused materials, and shall fi 11 and <br />dress all holes and cavities made for convenience, and leave all areas in good <br />order and condition, subject to the approval of the PROJECT MANAGER. <br />1.3 Measurement and Payment <br />No measurement for payment shall be made for mobilization and demobilization. <br />Payment of two-thirds of the lump sum price bid will be made with the first <br />monthly progress payment after completion of the work described above for <br />mobilization. Payment of one-third of the lump sum price bid will be made <br />with the final progress payment for the work if demobilization has been <br />completed. If the price bid for mobilization and demobilization is greater <br />titan 15 percent (15%) of the total contract price, invoices supporting the <br />mobilization costs will be required before payment is approved. <br />-4- <br />