Laserfiche WebLink
II. PROJECT WORK DESCRIPTION <br />Project Summary <br />The Sunlight mine site has been ordered to be reclaimed by the Colorado <br />Department of Natural Resources, Mined Land Reclamation Board (the Board). <br />The operator of the mine failed to comply with regulatory requirements for an <br />extended period of time, resulting in revocation of the mining permit and <br />forfeiture of the reclamation performance bond being held by the Mined Land <br />Reclamation Division (the Division). The Board has directed the Coal <br />Regulatory Section of the Division to secure reclamation of the site using <br />funds obtained from the forfeited performance bond. <br />The Sunlight mine site consists of two disturbed areas located on the north <br />and south sides of County Road 117. Reclamation work to be accomplished under <br />this contract consists of sealing two mine openings, backfilling and regrading <br />one of the sealed openings, and demolishing and removing certain mine <br />structures and electrical utilities. <br />Adequate rights-of-way needed for access to the project area and within the <br />working area limits specified for this project have been acquired by or on <br />behalf of the OWNER. <br />III. PROJECT WORK SPECIFICATIONS <br />1.0 MOBILIZATION/DEMOBILIZATION <br />1.1. Description <br />This specification covers the CONTRACTOR's operations for: <br />a. Payment of premiums for bonds and insurance acquired specifically <br />for the construction of this project, including premiums for <br />performance and payment bonds; <br />b, Movement of personnel, equipment, operation supplies, and <br />incidentals to the project site, but not within the work limit area; <br />c. Preparatory work at the construction site; <br />d. Demobilization of CONTRACTOR'S equipment and all other facilities, <br />final project clean-up. and for ail other work for which payment is <br />not otherwise provided for under the contract. <br />The temporary works and Construction plant may include, but not be limited to <br />the following: <br />a. Workshops, offices, storage yards, and construction plant and <br />equipment including spare parts, fuels, and oil; <br />b. Sanitation facilities, communication facilities, and sprinkler <br />trucks; <br />c. CONTRACTOR'S electrical power system; <br />d. Other items such as water, compressed air, etc.. not specifically <br />listed but required for the functioning of construction activities, <br />-3- <br />