Phase II-III Summary No. 3 Page 2 043-2170 <br />Field Monitoring and Testing Activities <br />Golder observed construction activities associated with Phase II-III Extension earthworks. All <br />construction materials and soil materials placed were verified as suitable, and construction methods <br />were in accordance with project specifications. <br />Golder visually observed the placement of DCF in the Phase II-III Extension area. Golder CQA <br />monitors (one monitor per dozer when dozers are greater than 50 feet apart) observed DCF <br />placement and verified minimum thickness of 2 feet for finish grade, and 4 feet for haul traffic (i.e., <br />Caterpillar Model 740 articulated trucks). <br />Laboratory Tests <br />Golder obtained one QA sample of Drain Cover Fill (DCFx-QA-O1) associated with Phase II-III <br />extension construction for laboratory index testing to determine suitability of materials used. The <br />completed tests met the requirements of the specifications and the results are presented in <br />Attachment B. <br />Meetings <br />CC&V held a Weekly Contractors' meeting on September 21, 2004. Items discussed included <br />Safety, Enviromnental, Schedule, QC documentation, and CQA. The next weekly meeting will be <br />held on September 28, 2004 at 10:00 AM. <br />Golder Personnel On-Site <br />A summary of all Golder CQA personnel on site during this reporting period is presented in <br />Attachment A. <br />Sincerely, <br />Ron DiDonato <br />Project Resident <br />en~~u-mssm~~nR ~s-s~m,na zs zooa Golder Associates lnc. <br />