Laserfiche WebLink
PUase IVc SucnmaryNo. 15 Page 3 043-2170 <br />Golder observed geomembrane deployment, documenting ambient temperature, panel dimensions, <br />thickness, seaming, tie-in overlap, and seam testing (trial seams, pressure testing). Geomembrane <br />installed in the Phase Nc OSA met the project specifications. <br />Golder visually observed the placement of DCF in the Phase Nc OSA area. Golder CQA monitors <br />(one monitor per dozer when dozers are greater than 50 feet apart) observed DCF placement and <br />verified minimum thickness of 2 feet for finish grade, and 4 feet for haul traffic (i.e., Caterpillar <br />Model 740 articulated trucks). <br />Golder observed placement of HVSC piping in the Phase Nc OSA, verifying installation and layout <br />per the project plans. <br />Laboratory Tests <br />Golder obtained one QA sample of soil liner fill (SLFc-QA-18) and one QA sample of drain cover <br />fill (DCFc-06) for laboratory index testing. The completed test samples met the requirements of the <br />specifications and the results are presented in Attachment B. <br />Meetings <br />CC&V held a Weekly Contractors' meeting on August 17, 2004. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. The next weekly meeting will be held on <br />August 24, 2004 at 10:00 AM. <br />Golder Personnel On-Site <br />A summary of all Golder CQA personnel on site during this reporting period is presented in <br />Attachment A. <br />Sincerely, <br />Ron DiDonato <br />Project Resident <br />en~~rv~~sw~~u-n~a~oxi zooa Golder Associates lnC. <br />