BMRI Actions Chronology <br />Date Event/Activity <br />February -March 1999 BMRI submitted to the Division of Minerals and Geology an <br />interim report (Feb. 5, 1999) and final response plan (TR-26; <br />March 22, 1999) <br />June -July 1999 BMRI received approval to construct the enhanced <br />evaporation system; pumps installed in monitoring wells M- <br />18, M-19, M-28, and M-29; an additional pump was <br />installed in M-20 <br />August 1999 Active water treatment facility mobilized to site (August 27, <br />1999); testing completed and system commissioned for <br />actual discharge on September 3, 1999 <br />CDPS discharge permit application was submitted on August <br />2C, 1999 <br />Minimal Discharge Industrial Wastewater permit application <br />submitted on August 30, 1999 <br />