-3- <br />Minor Revision No. 29 was submitted on February 4, 1988 and requested <br />reclamation delays on certain areas, signage changes, and extension of Haul <br />Road E5. The revision was approved on March 16, 1988. <br />Minor Revision Ho. 30 was submitted on April 18, 1988 and requested permission <br />for Haul Road A and dragline erection pad construction. The revision was <br />approved on April 25, 1988. <br />Technical Revision No. 13 was submitted on February 17, 1988 and requested a <br />change in the water monitoring plan. The revision was approved on <br />April 26, 1988. <br />Minor Revision No. 31 was submitted on April 25, 1988 and requested <br />modification of the shrub and tree planting list. The revision was approved <br />on May 4 , 1988 . <br />Technical Revision No. 14 was submitted on February 17, 1988 and requested a <br />northern extension of the Wadge Pit and dragline deadhead route modification. <br />The revision was approved on July 22, 1988. <br />Minor Revision No. 32 was submitted on September 29, 1988 and requested a 770 <br />B dragline deadhead route between the Wadge and Wolf Creek Pits and relocation <br />of topsoil stockpile JJ. The revision was approved on October 11, 1988. <br />Technical Revision llo. 15 was submitted on August 4, 1988 and reouested a <br />change in the sediment (contained in sediment ponds) monitoring frequency. <br />The revision was approved on November 22, 1988. <br />Technical Revision No. 16 was submitted on December 28, 1988 and requested <br />reclamation delays on Auger Area c (fora possible site of an underground mine <br />portal in the future), the Wadge Scraper pit area, and the lower Wadge Haul <br />Road ramp. The revision was approved on March 10, 1989. <br />Minor Revision No. 33 approval was issued as a field minor revision to allow <br />reclamation delay around the solid waste disposal area (Auger Area ;, ). Tne <br />revision was approved with conditions on June 13, 1989. <br />Technical Revision tJo. 17 was submitted on April 18, 1989 and reouested <br />extension of the north Wadge Pit deadhead route, modification of the surface <br />water drainage control plan, and access roads to sediment ponds 004 and 008. <br />The revision was approved on November 9, 1989. <br />Technical Revision IJo. 18 was submitted on Cctober 4, 1989 and requested an <br />update of the entire surface water control plan to reflect current reclaimed <br />topography and ground conditions at the mine site. The revision was approved <br />on December 27, 1989, <br />