Memo - Carl Mount - 3 - December 26, 1989 <br />Multiple Shift Work - Other Cost Considerations (continued) <br />4) Floodlighting system costs are added to the estimate as necessary to <br />provide minimum visibility necessary to conduct operations safely. <br />Additional Equipment Costs <br />Based on further review of cost data contained in the CRG and CECG, it appears <br />that the fuel cost value shown in the CRG does not include the cost of a <br />fueling truck, fueling labor, and fuel storage costs. As such, the cost of a <br />fueling rig and operator should be added to the estimate in order to provide a <br />more accurate estimate of anticipated project costs. A cost worksheet for a <br />fueling rig and operator is attached. <br />Jern <br />2467E <br /> <br />