Laserfiche WebLink
<br />Page 2 <br />May 22, 1995 but was suspended on the 24th because the ground was <br />too wet to support equipment. Recordable moisture continued on May <br />26, 27, 28, 29, 30 and 31. June saw the following days of <br />precipitation before finally starting, albeit under less than ideal <br />conditions, the work again on June 22, 1995. The days were June 2, <br />3, 4, 9 and 17. Due to the extreme wet conditions noted above P&M <br />claims a climatic condition delay of 22 days on the project <br />schedule and would anticipate completion by November 22, 1995 <br />instead of the listed deadline of October 31, 1995. <br />Should you have any questions regarding this material, please <br />contact me at the mine site. <br />Sincerely, <br />David Beverlin <br />Resident Engineer <br />