Reclamation History of the Hayden Gulch Mine <br />The 8.9 acres of this bond release aze the remnants of a lazger (former) permit area. The Hayden <br />Gulch mine has been in existence since January 1978, first under Permit 77-99, and then under <br />Permit C-1980-003. The initial C-1980-003 permit of the Hayden Gulch Mine described a mine <br />site of 1,27213 acres, and a coal loadout facility of 134-acres (the coal loadout is located <br />approximately two miles southeast of Hayden)14. Of 517 acres planned for disturbance15 in 1980, <br />355 acres at the mine site and 54 acres at the loadout had been disturbed as of January 23, 198716 <br />Mining ceased, and reclamation operations at the mine site followed immediately. The disturbed <br />azeas of the mine pit (azeas east of Routt County Road 53) were completely backfilled and <br />graded, topsoiled and seeded by the end of 1986~~. The disturbed areas of the mine-site office, <br />shop, and wazehouse facilities, located west of Routt County Road 53 (RCR 53), were reclaimed <br />in the fall of 198718. Depending on steepness of slope and availability of equipment, seed was <br />applied by drill seeding, hydro seeding, and hand broadcasting. Three different seed mixes were <br />used during reclamation. The reclaimed areas were not fertilized or irrigated. <br />The loadout was withdrawn from Permit C-1980-003 in 199319 and permitted under Permit C- <br />1992-081. The permit azea of Permit C-1980-003 was re-described as 1,276 acres in 199620, of <br />which 362 acres had been disturbed. Subsequent to bond releases SL-O1, SL-02, and SL-03, <br />described below, the permit area was reduced to 6.8 acres. The permit azea was later redefined <br />(resurveyed) as 8.9 acres21. <br />This bond release application applies to the entire 8.9 acres of the permit, consisting of a 1.14- <br />acre slump azea (Slump) and three shrub plots (Pazce1003 of 1.62 acres, Pazcel HG-8 of 5.13 <br />acres, and Parcel E consisting of 1.03 acres) These four parcels (areas) are shown on Figure 1 of <br />the bond release application (Final Bond Release Application, Hayden Gulch Mine Permit <br />Boundary and Revegetation Sequence). These four parcels incurred an extended bond liability <br />periods due to shrub augmentation planting on three of the pazce[s, and slump repairs on the <br />other. The liability on the shrub areas was extended to June 5, 2001. The liability on the slump <br />area was extended to 200422. These azeas were not included in SL-03 (Phase II and Phase III). <br />Reclamation activities remaining were limited to establishing vegetation (shrub augmentation) on <br />~3 Findings, November 23, 1981 <br />14 Findings, Permit Revision No. 1, August 17, 1984 <br />'S Findings, November 23, 1981 <br />16 Findings, Permit Renewal, January 23, 1987 <br />~~ Findings, Permit Renewal No. 3, January 1997; SL-O1, Proposed Decision <br />i8 Findings, Permit Renewal No. 3, January 1997; SL-02, Proposed Decision <br />19 Technical Revision 61, 6/4/1993 <br />2° Technical Revision 62, 4/19/1996 <br />Z' Technical Revision 68, January 13, 2000 <br />zz Division letter of may 13 1998, Re: Hayden Gulch Mine, Permit No. C-80-003 Minor Revision <br />MR-13 Slump Mitigation <br />Hayden Gulch Mine Page 6 July 31, 2006 <br />SL-04 <br />