<br />Table 1: Proposed Actions on RDA <br />Structure Actiou Start End <br /> Date Date <br />Perimeter Diversion Route water from the Complete NA <br />Ditches crest of the pile to the <br /> gabion-lined ditches. <br /> Submit M.R. to change September 4, 1998 N.A. -Approval <br /> armoring from gabion expected withing 1 - <br /> baskets to rip-rap. 2 weeks <br /> Fill and compact piped September 3, 1998 September 30, 1998 <br /> azea adjacent to East and <br /> West Perimeter Ditches. <br /> Stake revised trapezoidal <br /> ditch configuration: <br /> Place rock. Upon receipt of Ten weeks following <br /> MR approval. MR approval. <br /> Prepare engineering Three weeks NA <br /> certification of perimeter following <br /> ditch installation. completion of <br /> armoring. <br /> Seed working area with Three weeks, NA <br /> sterile winter wheat. following <br /> completion of <br /> arTnoring. <br /> Hydroseed working azea April 1, 1999 May 15, 1999 <br /> in spring with permanent <br /> seed mix. <br />