Laserfiche WebLink
6Z Measurement and Payment <br />Payment for this task will be reflected under Item six (6) of the Bid Schedule as an hourly <br />rate for a CAT D-7H or 215 FHP machine with operator. Bid hourly rates shall reflect the <br />CONTRACTORS estimate for equipment and personnel costs per hour to complete the <br />task. Measurements will be actual hours required to complete work outlined above and/or <br />as directed and approved by the PROJECT MANAGER. The hours outlined under Item <br />6 are NOT guaranteed. <br />PROJECT OBSERVATION <br />The PROJECT MANAGER will be at the project site periodically to monitor construction <br />activities and ensure that each work item is completed and wnstruMed to design <br />specifications. The PROJECT MANAGER will be available during regular business hours <br />(8:00 A.M. to 5:00 P.M.) on weekdays. Inspections will not be scheduled on weekend days <br />or holidays without prior approval of the PROJECT MANAGER. The following items must <br />be observed and approved by the PROJECT MANAGER before proceeding with additional <br />work: <br />1. Final contours of graded coal material prior to topsoil placement. <br />2. Depth of topsoil on coal material prior to revegetation. <br />3. Successful plug placement on the methane gas wells prior to backfilling and <br />revegetation. <br />4. Final grade and dimensions of ditch prior to geo fabric installation. <br />c:\hawk\bid2 <br />17 <br />