<br /> <br />• 20. According to Tom Anderson there may be a need to change the stacking tube from 100 foot <br />height to 120 foot height. If this is required, please make all changes in the document that may be <br />affected by this addition in height. <br />Response: Given that detailed engineering and design for the proposed mine facility <br />construction/modification activities is proceeding concurrently with permitting, <br />dimensions of specific structures and facilities are subject to modification to accommodate <br />design considerations. The discussions of mine facilities have been reviewed with this <br />consideration in mind and all dimensional references have either been deleted (if <br />dimensions are not an important consideration relative co potential project impacts, ie: <br />changes in conveyor widths which will not increase the associated disturbance area) or <br />noted as approximate. Where dimensions are noted as approximate, dimensional changes <br />due to design modifications are not expected to vary more than 20 percent from the <br />dimensions noted. Current design dimensions for all facilities are provided by the Mine <br />Facili[ies Summary (refer to pages 2.05-Sc [hrough 2.05-SfJ. Following comple[ion of <br />detailed design and construction, the Surface Facili[ies Map, (Map 3213), and any other <br />maps as appropriate, will be revised and re-submitted to reflect as-built dimensions. Please <br />see accompanying revisions. <br />21. "Equipment and Material Storage Areas" could become a liability unless cleaned up during this <br />reconstruction. Some of the items on Elk Creek near the explosives storage area could become a <br />significant hazard if they were to get into the drainage and obstruct the long culvert passing <br />under the coal storage piles. Please consider proper disposal of unused items in this location and <br />• the west terrace during this expansion project. <br />Response: In order to provide additional area for expansion of the existing Elk Creek soil <br />stockpile, a new explosive storage area will be established, the existing explosive magazines <br />will be removed, the Elk Creek culvert will be extended, and the entire new soil stockpile <br />area will be regraded. During facility removal and regrading activities, material and <br />equipment presently stored adjacent to Elk Creek and above the existing explosives <br />magazines will be removed and either disposed of or relocated to the existing East Yard <br />storage area. <br />22. Under your listing "Substation 1 ° on page 2.05.10, it states that "Delta-Montrose Electrical <br />Association will be responsible for all power line relocation activities." Will there be any need <br />for new access roads or work pads? '!f so, please indicate where this information can be located in <br />the existing document, or provide the information. <br />Response: Please refer to previous Response 3 above. The referenced discussion of <br />relocation activities for Substation 1 on page 2.05-10 has been expanded to include <br />information on the powerline relocation and associated disturbance. Please see <br />accompanying revisions. <br />23. Map E-3213 is lacking some of the labels for structures such as Conveyor IA. Please add the <br />needed labels to aid in referencing of this document with the narrative. <br />Response: Map 3213 has been revised to include additional labels for those facilities not <br />• currently identified as noted. Please see accompanying revisions. <br />