<br />The following figures should be used: <br />(1) Sloping and grading (1 acre) <br />dozer (75.00 per hr.) x 8 hrs - 5600.00 <br />(2) Hauling and spreading topsoil (1 acre) <br />1 scraper (75.00 per hr.) x 4 hrs - $300.00 <br />(3) labor For hand seeding <br />2 men (20.00 per hr.) x 4 hrs - <br />S 80.00 <br />(4) Cost of seed (enclosed estimate) - $ 64.72 <br />Total cost (mayor dist.) per acre - y1044.72 <br />Phased Operations - In regards to bonding, Mathias Concrete, <br />Inc., would commit to the following levels of disturbance in this <br />reclamation plan. (Please also refer to enclosed map.) <br />(1) 6 acres mayor disturbance <br />(2) 1.2 acres moderate disturbance <br />(3) 12.5 acres undisturbed <br />(4) Balance of affected acres to be released from liability <br />or minor disturbance. <br />We would not be mining in the undisturbed area for several years. <br />Sometime in the future, when it appeared that we would have to <br />move into this area, we would request a technical revision from <br />the M.L.R.D. which would then require a bond revision for this <br />specific area. <br />In addition, we intend to have the area we are now mining <br />(present 110 permit), fully reclaimed before moving into <br />undisturbed area. we will periodically ask for release of <br />liability for specific acreages as reclamation is accomplished, <br />in the next feu years. <br />This revised, Pre-mining and Mining Map, if approved, should be <br />substituted For the original and become part of 112 permit. I <br />will send five additional copies after approval. <br />Thane /)~ <br />Thomas G. Mathias - Mathias Concrete, Inc. <br />