ZZ 107,516 164,560 136,649 164,560 164,560 164,560 164,560
<br /> 156,000 112,933 0 0 112,933 112,933
<br />CCC 0 156,816 0 156,816 156,816 156,816
<br />DDD 75,200 122,452 0 122,452 122,452 122,452
<br />EEE 75,700 0 0 0 0 0
<br />?? 29,171 0 0 0 0 0
<br />?? 31,520 0 0 0 0 0
<br />
<br />Total 1,894,850 1,244,219 1,398,115 1,458,131 1,558,803 1,238,717 2,045,384
<br />The maximum volume of topsoil to be replaced at the Seneca II-W Mine was
<br />approximately 2,045,384 LCY. The volume the Division used in its estimate
<br />was 1,894,850 LCY. The volume SCC suggests using is 1,224,219 LCY.
<br />The Division has actually underestimated the amount of topsoil to be replaced
<br />by approximately 150,000 LCY. Based on the above table, the Division will
<br />not change tasks 050-085.
<br />11. Revegetation Work: Task 093 -Drill Seed Cover Crop -Page 28 of Tab 22
<br />states that cover crops will be seeded, possibly independently of other seeding
<br />activities. Nothing was found in the PR-OS submittal removing this reference.
<br />Therefore, at this time, this task well remain.
<br />Task 096 - Hydroseed Mix 1 -Page 29 of Tab 22 references the hydroseeding
<br />task. Nothing was found in the PR-OS submittal removing this reference.
<br />Therefore, at this time, this task will remain.
<br />Tasks 098-103 -Shrub and Tree Transplants -Although this was not a part of
<br />the SCC memo, the Division has changed the transplant failure rate to more
<br />accurately reflect the site conditions (as was done at the Yoast Mine). The
<br />failure rate was changed from 85% to 40%.
<br />Task 104 - Hydromulch 50 Acres - As with task 096 above, page 29 of Tab
<br />22 references the hydroseeding task. Nothing was found in the PR-OS
<br />submittal removing this reference. Therefore, at this time, this task will
<br />remain.
<br />Task 106 -Drill Seed Cover Crop on TAHR -The Division did not see a
<br />reference to drill seeding a cover crop on the TAHR in Tab 22. Therefore,
<br />this task will be removed from the estimate.
<br />Task 110 -Straw Mulch TAHR -The Division did not see a reference to
<br />placing straw mulch6 on the TAHR in Tab 22. Therefore, this task will be
<br />removed from the estimate.
<br />12. Miscellaneous and Equipment Mobilization: Task 118 -Rill and Gully and
<br />Road Maintenance -SCC states that the use of a D3C dozer is overkill when a
<br />13