MANAGER and CERTIFYING ENGINEER may require CONTRACTOR to test up to as much as <br />twenty percent (20%) of factory fusion welds (non-destructive air pressure test) in the field to verify <br />factory test results. Additional testing at CONTRACTOR'S expense will be required if failed tests aze <br />obtained in the field. <br />3.07 FIELD SEAMS: <br />A. Seam Layout <br />Seams shall be oriented parallel to the line of maximum slope, i.e., oriented down, <br />not across the slope. In corners and odd-shaped geometric tocations, the number of <br />field seams shall be minimized. <br />2. No horizontal or base T-seam or tie-in seams shall be closer than five (5) feet from <br />the toe of the slope. Seams shall be aligned to prevent wrinkles and "fishmouths". [f <br />a 5shmouth or wrinkle is found, it shall be relieved and capped. <br />3. Panels of geomembrane will have sufficient overlap provided to allow peel tests to be <br />performed on the seam. <br />B. Seaming Method <br />The procedure used to temporarily bond adjacent panels together shall not damage <br />the geomembrane; in particular, the temperature of hot air at the nozzle of any spot <br />welding appazatus shall be controlled such that the geomembrane is not damaged. <br />2. CONTRACTOR shall use double fusion welding as primary method of seaming <br />adjacent field panels. <br />• a. For cross seam tees associated with fusion welding, CONTRACTOR shall <br />patch panel intersections consisting of 3 or more panels and extrusion weld <br />to a minimum distance of 4 inches on each side of patch. The edge of the <br />sheet shall be ground to a 45° angle prior to welding. <br />b. Place a protective layer, e.g., insulting plate or fabric, beneath hot welding <br />apparatus after usage. <br />c. When subgrade conditions dictate, use a moveable protective layer directly <br />below each overlap of geomembrane that is to be seamed to prevent buildup <br />of moisture between sheets and prevent debris from collecting around <br />pressure rollers. <br />d. Remove seaming sheets and excess geomembrane trimmed to provide <br />required overlap. <br />3. Use conventional extrusion welding as a secondary method for seaming between <br />adjacent panels and as a primary method of welding for detail and repair work. <br />a. Purge heat-degraded extrudate from barrel of extruder under the following <br />conditions: <br />Prior to beginning a seam. <br />2. Whenever extruder has been inactive. <br />Section 02776 Page 14 of 20 October 25, 2000 <br />Geomembrane Golder Associates Revision 8 <br />D9PHASEw PSSA CERTe1PPENDICIE541PPENDIX E TECHNICAL SPECIFICATIONS\99)-l°9902]161RB.DOC <br />