DIVISION l -GENERAL REQUIREMENTS <br />SECTION 01700 -CONTRACT CLOSEOUT <br />LO1 CLOSEOUT PROCEDURES <br />The following project closeout procedure defines the responsibilities of the Contractor, Owner <br />and Engineer in closing the project: <br />Step 1: Contractor advises the Engineer in writing that he has reached "Substantial <br />Completion" and provides a list of items to be completed or corrected. <br />Closeout may be conducted by areas or portions of the work if requested by the <br />Owner. <br />Step 2: Engineer observes the work to determine if it is substantially complete, and <br />issues a "Punch List" of items to be completed or corrected. <br />Step 3: ' Contractor completes and/or corrects all punch list items and notifies the <br />Engineer in writing that his work is ready for final inspection. <br />Step 4: Engineer makes final examination. When the work is found to be acceptable, the <br />Engineer will prepare a final construction report and as-built plans. <br />END OF SECTION <br />Draft -Technical Specifications <br />01/99 Section O] 700 - Page I of ] <br />