• <br /> The following figures calculated for reclamation of this site were based on the disturbance on the <br /> west and northwest end of the property. <br /> TABLE L-1 SUMMARY OF RECLAMATION COSTS <br /> Costs Amount <br /> DISTURBANCE COST TOTAL 47,450.00 <br /> CONTRACTOR MOB/DEMOB (8%) 3,796.00 <br /> OVERHEAD (18.5%) 8,778.25 <br /> ADMINISTRATIVE (5%) 2,811.41 <br /> TOTAL PROPOSED BOND 60,024.25 <br /> DISTURBED ACREAGE 22.75 <br /> BOND COST PER ACRE 2,638.43 <br /> Notes: Contractor mobilization\demobilization bases on Colorado Department of <br /> Transportation estimate. <br />