Pumping Vault <br />The pumping vault will be constructed from precast concrete or from cast-in-place <br />concrete. Pipe penetrations in the pumping vault will also be grouted. Prior to <br />construction of the vault, the foundation will be inspected, loose or soft materials will <br />be over-excavated and replaced with structural fill, and approved by the field <br />engineer prior to placement of the floor slab. <br />Irrigation Pipeline <br />A specific Constmction QA/QC plan will be developed after the evaluation of the <br />existing pipeline has been completed, sections needing replacement have been <br />identified, and the most appropriate construction method (slip-lining or trenching) has <br />been selected for these sections. <br />Hvdrostatic Testing <br />Hydrostatic testing of the completed pipeline shall be performed in the presence of <br />the Owner's Representative and in accordance with the construction specifications. <br />Pressure testing shall be completed on all installed HDPE pipe prior to placing fill <br />over the pipes or backfilling the receiver pipe. Pipes shall be tested at the required <br />internal pressure for a minimum of three (3) hours after the pressure in the pipe has <br />stabilized. The duration of the expansion phase and pressure dissipation phases shall <br />be consistent with the manufacturer's recommendations. The pipeline shall be <br />inspected for leaks. In the event that leaks are found, the pressure shall be allowed to <br />dissipate and the water removed prior to making the necessazy repairs. The pipeline <br />shall be retested until a passing test is achieved prior to placing fill over the pipe or <br />backfilling receiver pits. <br />Battle Mountain Resources, Inc. 2S Telesto Solutions, /nc. <br />rvwmie<m~zt~-tae.mom(sua.u~s)\SanwiNYrtnn nmenament- west wt mvagemem~va aepon~rorswmm+iwremmeni va.aoc October 2006 <br />