Laserfiche WebLink
Mr. Forest Leaf, P.E. Page Three <br />December 14, 2004 <br />January 1, 2005: Start the preliminary CFCP by ACE. <br />February 25, 2005: Completion of the preliminary CFCP by ACE. <br />March 30, 2005: Submittal of preliminary CFCP and CLOMR to Weld County, <br />DMG, and USACE for review of the plan and CLOMR package. <br />Apri18, 2005: Submittal of CLOMR to FEMA for review. <br />July 1, 2005: Receive FEMA's conditional approval of CLOMR. Receive DMG <br />and USACE's review comments. <br />September 1, 2005: Complete final CFCP and obtain all permits. <br />November 1, 2005: Begin construction. <br />ACE will make realistic efforts to accelerate the above schedule, however, the actual <br />completion schedule will ultimately be dictated by review times at the various regulatory <br />agencies. <br />If you have any questions or comments concerning these review comments for the please <br />do not hesitate to contact me. <br />Sincerely, <br />ANDERSON CONSULTING ENGINEERS, INC. <br />ar~ <br />~~~- <br />Chris J. Pauley, P~ <br />Project Manager - - <br />CJPBAA/tlt <br />Attachments: A. "Findings of Fact, ...", December 6, 2004. <br />Cc: Mr. Chris Varra, Vana Companies, Inc., w/o attachments <br />Mr. Bradford Janes, Vana Companies, Inc., w/o attachments <br />Mr. Tom Sclu-einer, DMG, w/o attaclunents <br />COVC03-Ol F Leaf LhLdoc <br />