Laserfiche WebLink
Phase tVb Weekly Summary No. 13 Page 2 003-2203 <br />. Ames continued placement of Structural Fill (SF) in the Phase IVb azea. Ames placed SF, hauled from <br />the SLF reject pile, to the Substation Hill south and west slope. Ames also continued slope <br />recontouring and re-compaction in the Phase IVb azea on Substation Hill. <br />Ames continued drilling perforation holes into the 26-inch High Volume Solution Collection System <br />(HVSCS) piping at the staging azea neaz the old LOB location. <br />Ames continued Drain Cover Fill (DCF) removal near the Phase III /Phase IV b PSSA east end berm in <br />preparation of end berm construction. <br />Poly-Flex began deployment of 100-mil smooth (upper) LLDPE geomembrane in the Phase IVb PSSA. <br />Poly-Flex deployed 100-mil smooth LLDPE geomembrane over an area of approximately 76,151 <br />squaze feet in the Phase IVb PSSA during this reporting period. Geomembrane panels U-O1 through U- <br />19 were deployed, seamed, and tested by Poly-Flex. Destructive fusion seam samples DFu-Ol through <br />DFu-06, were mazked and removed. <br />On Thursday, April 17, 2003, Poly-Flex cleared, cleaned, repaired and tested two aeeas of previously <br />deployed (2002 construction) 100-mil single sided textured LLDPE and 100-mil double sided textured <br />geomembrane that was damaged by rock fall and equipment. Golder identified and inspected damage <br />panels and Soil Liner Fill prior to repair. Each repair was tested by Polyflex and documented. <br />• Phase IVc <br />Ames resumed limited cut to fill activities within the northern limits of the Phase IV c area. SF and <br />oversize stockpiles were created for future removal or haul out. <br />Ames constructed a geogrid and Select Structural Fill (SSF) cap over UG-279. Ames placed two layers <br />of geogrid in accordance with the drawings and specifications. Approximately 2779 square feet of <br />geogrid was placed in the working. <br />Field Monitoring and Testing Activities <br />Golder observed construction activities associated with Phase IV earthworks. All construction <br />materials and soil materials placed were verified as suitable, and construction methods were in <br />accordance with project specifications. Removal of oversized and deleterious material from all fill <br />areas was observed. Golder observed Structural Fill (SF) placement in Phase IV for materials, lift <br />thickness, moisture content, and compactive effort. <br />Golder observed placement of SLF in Phase IVb for subgrade prepazation, thickness, compaction, <br />moisture content, and materials. Golder conducted one informational density and moisture content <br />test to verify SLF placed complied with the specifications. <br />Golder observed and documented remediation activities associated with the Phase IV underground <br />• working construction. Workings were designated as Shallow or Deep as defined in the drawings. <br />Phase lVb li AprO.Opr19, 1001 Golder Associates inc. <br />