Laserfiche WebLink
I • 4. Reclamation Timetable <br /> <br />The time for reclamation is shown below. Exhibit L: Reclamation Costs describes the worst case <br />bond scenario. <br />Table E-2 <br />Task # Description Time Needed <br />Months <br />1 Prepaze sediment pond and place berm <br />along I-70 0.25 <br />2 Strip topsoil from Pit lto stockpile at <br />northwest corner of Pit 1 0.5 <br />3 Bring in portable crusher, screen plant, <br />stackers, truck scale, and scale house. 0.25 <br />4 Mine Pit 1 29.7 <br />5 Reclaim Pitl and mine Pit 2 30.0 <br />6 Reclaim Pit 2 and mine Pit 3 53.3 <br />7 Reclaim Pit 3 and mine Pit 4 72.8 <br />8 Reclaim Pit 4 1.0 <br />9 Remove all facilities 0.5 <br />10 Reseed and mulch wetland azeas 0.25 <br /> Total months 188.5 <br /> Total years 15.7 <br />IS Road Pit February 07 E-4 <br />