June 24, 2003 -18- 003-2203.7 <br />I • 2.11 Select Drain Cover Fill <br />Ames began and completed placing SDCF in the Phase IVb PSSA in June 2003. Ames processed <br />SDCF during the month of February 2003. Ames processed the borrow material through a crusher mill <br />and screening plant and temporarily stockpiled the SDCF material at their crusher yazd for haulage. <br />Ames placed approximately 3,500 cubic yards of SDCF in the PSSA. SDCF was placed in a <br />minimum 2-foot thick lift around the vertical risers, 3 feet beyond the extents of the vertical risers. <br />Ames placed SDCF in a horizontal lift within the PSSA sump. <br />2.12 Drain Cover Fill <br />Ames began placing DCF in the Phase IVb PSSA in September 2002, and completed placement in <br />June 2003. Ames processed DCF from August 2002 to June 2003 by screening Pad No. 4 material <br />and crushed Cresson Ore over a vibrating one and one-half inch screen to remove oversize material <br />from the borrow source. Ames placed approximately 85,552 cubic yards of DCF in the PSSA. DCF <br />was placed in a minimum 2-foot thick lift over the geomembrane and in a 10-foot thick lift where <br />• Caterpillar 777 haul trucks traveled over the geomembrane. During fill placement, PVC grade markers <br />were placed at grade breaks and on a maximum 50-foot by 50-foot grid. After DCF placement, PVC <br />grade makkers were removed, and Ames performed any additional grading required. Ames placed DCF <br />in an uphill direction on any slopes steeper than 4H:1 V. <br />r 1 <br />LJ <br />L\00\2303\0~001pnICertP55A0603\003330J.0000.00303Rep.doc Golder Associates <br />