Laserfiche WebLink
June 24, 2003 -10- 003-2203.7 <br />2.1.1 Remediation of Shafts, Stopes, and Shallow Surface Pits <br />The following is the general approach used to remediate isolated shafts and shallow surface pits: <br />For open workings where the depth to competent bedrock is less than 7 feet to <br />the final SLF subgrade surface, the excavations were backfilled with CSB to <br />approximately 10 feet below the finished surface grade. The surface of the CSB <br />was compacted using the shovel from a CAT 330b excavator. A 3-foot minimum <br />CP was cast into the shafr and allowed to cure for a minimum of 7 days. A <br />minimum ~-foot thick layer of CR was then placed onto the CP. SF was then <br />placed to the final grade, as needed. In some cases, the excavation did not <br />require placement of CSB prior to placement of the CP and CR. <br />• For open workings where the depth to competent bedrock was greater than 7 feet <br />to the final SLF subgrade surface, the excavations were backfilled with CSB to <br />3 feet below the soil bedrock interface. The surface of the CSB was compacted <br />using the shovel from a CAT 330b excavator. A 3-foot minimum CP was cast <br />into the shaft and allowed to cure for a minimum of 7 days. A minimum 7-foot <br />thick layer of CR was then placed onto the CP. After the CR was allowed to <br />cure, SF was then placed to the final grade, as needed. Due to the depth of <br />weathered bedrock, working UG-494 was remediated using a 10-foot thick <br />concrete friction plug combined with the typical 3-foot CP plug and 7-foot thick <br />CR plug. In some cases, the excavation did not require placement of CSB prior <br />to placement of the CP and CR. <br />For collapsed workings extending deeper than 25 feet and where the depth to <br />competent bedrock was less than 7 feet to the final SLF subgrade surface, the <br />collapsed materials were excavated to a depth of 25 feet below finished grade. <br />The excavations were either backfilled with CSB to approximately 10 feet below <br />the finished grade or shaped for the CP at a workable depth below 10 feet. The <br />surface of the CSB or existing material was compacted using the shovel from a <br />CAT 330b excavator. A 3-foot minimum CP was cast into the shaft and allowed <br />to cure for a minimum of 7 days. A minimum 7-foot thick layer of CR was then <br />placed onto the CP. After the CR was allowed to cure, SF was then placed to the <br />final grade, as needed. In some cases, the excavation did not require placement <br />of CSB prior to placement of the CP and CR. <br />For collapsed workings extending deeper than 25 feet and where the depth to <br />competent bedrock was greater than 7 feet to the final SLF subgrade surface, the <br />collapsed materials were excavated to a depth of 25 feet below finished grade. <br />The excavations were either backfilled with CSB to approximately 3 feet below <br />the soiUbedrock interface or shaped for placement of the CP. The surface of the <br />CSB was compacted using the shovel from a CAT 330b excavator. A 3-foot <br />minimum CP was cast into the shaft and allowed to cure for a minimum of <br />7 days. A minimum 7-foot thick layer of CR was then placed onto the CP. After <br />the CR was allowed to cure, SF was then placed to the final grade, as needed. <br /> <br />I:~amziona~oou'mC.nP55A06oA0WZZOl.aa00.olauRep.e« Golder Associates <br />